1978 Parking Deck Removal Update

FAQ’s Regarding the Removal of the Deck

 

May 2, 2023 – From the Deck of City Manager Eric Waara:

All,

Weโ€™re sure some people are wondering whatโ€™s going on with the parking deck and the Lakeshore Drive Corridor Redevelopment Project.

Since the last email, we were able to work with the contractor (MJO) and the engineer on โ€œvalue engineeringโ€ which means we were able to cut some things out and we were able to modify the design on some elements to build them at a lower cost. Last week, the City Council was presented an overall plan which reduced the contract price by change order and added funds to the project to close the remaining gap in the funding. MEDC was not able to increase their funding amount over the $1,000,000 we received under the Revitalization and Placemaking Program rules. The Council approved the plan so the project can move forward. We are just awaiting MEDCโ€™s concurrence with the plan to finalize the contract.

We could go through an exhaustive list of the changes, many of which were simply buying less of some things, but the project scope is still the same:

ยทย ย ย ย  The deck will be removed

ยทย ย ย ย  There will be two parking lots on the ground

ยทย ย ย ย  There will be sidewalks on both sides of Lakeshore Drive

ยทย ย ย ย  There will be two large rain gardens north of Pewabic Street between the parking lot and the sidewalk

ยทย ย ย ย  Around the parking lots will be landscaped and there will be landscaped islands along the south side sidewalks, including trees

ยทย ย ย ย  Street lighting will be installed

ยทย ย ย ย  The pedestrian walkway and gathering area will be built between Michigan Made and the Print Shop

ยทย ย ย ย  That walkway will have a โ€œgateway archโ€, overhead lighting, plantings, etc. and will lead to a sidewalk through the parking lot to stairs down to the trail

 

So, whatโ€™s next? In the coming weeks weโ€™ll be able to get a firm schedule and work sequence from MJO so we can start nailing down dates, locations, etc. Soon youโ€™ll be hearing from us on a lot of things like parking, closing of those deck-facing doors, trash collection, delivery access, when the weekly meetings will be, and so on. What we do know at the moment:

ยทย ย ย ย  MJOโ€™s subcontractor who will be doing the demo has an extensive list of experience in demolishing post-tensioned structures like this deck.

ยทย ย ย ย  If everything goes according to plan, they plan to start first with taking that breezeway off the Hall Building and making any needed repairs to the faรงade where the breezeway was attached.

ยทย ย ย ย  They plan to start deck demolition on the east side. The current goal is to start right after Memorial Day.

ยทย ย ย ย  The west side will stay open for awhile, and then will be demolished after the east side is down.

ยทย ย ย ย  They are expecting that each side will take about 3 weeks to take down. Once the deck is actually down everything as far as access, etc. gets a lot easier.

ยทย ย ย ย  Depending on which side of the deck theyโ€™ll be demolishing the waterfront trail will be detoured. When they are working on the east side people will be detoured toward the water and onto the Pier about midway. When they are working on the west half, pedestrians and bikes will need to use the dock until midway.

ยทย ย ย ย  For those of you abutting the deck, the contractor will be sending in people to do a survey of your building to document conditions before the demolition starts.

 

We might even have more detail on dates, etc. as soon as this week. As soon as we have more information weโ€™ll be sharing it.

 

And for those who had met with the team from Progressive on April 10 and 11 โ€“ they will be circling back around with their observations and recommendations. However, it might be a month or two.

 

Eric T. Waara, P.E.

Houghton City Manager